Capital Project 2024 Phase 3

Phase III - Courtyard and District Office
February 2026
The General Trades Contractor completed the installation of the gypsum wall board including all finishing work such as mudding, taping, and sanding. The Plumbing Contractor completed the in-wall plumbing rough for the new corridor drinking fountain located outside the new business suite. The Electrical Contractor relocated an existing electrical panel from within the old computer lab to the new electrical closet directly outside the new business suite. Additionally, the Electrical Contractor pulled new wiring through previously roughed conduit and is waiting for the walls to receive primer and their 1st coat of paint before installing devices.
Outside, the General Trades Contractor installed rigid insulation and exterior grade sheathing with a pre-applied vapor barrier at the courtyard infill. Additionally, the roof was tied into the new wall system per the details provided by the Architect.
Regarding modifications to the project, a change order has been processed to add wall tile to the new wall sections within corridor 002 which is the corridor that adjoins the District Office and Business Suite. That tile order has been released, and the General Trades Contractor is working to get that tile onsite. A few other recent modifications were received in regards to infilling a portion of the transaction window at the vestibule, swapping a framed doorway into a cased opening, removing an existing steel column and relocating with a new smaller steel column, and shifting the interior set of vestibule doors. That change has been received by the applicable contractors and is being priced up
for review. Priming and painting of the rooms not affected by the change will start in March.
January 2026
The General Trades Contractor began installing the insulation and gypsum wall board. They are tracking about 80% complete with the remaining 20% to be completed within the first two weeks of February. The plumbing Contractor completed the in-wall plumbing rough within the Business Suite for the new Kitchenette and began installing new pipe for the Corridor drinking fountain. The Mechanical Contractor completed all above ceiling and in-wall rough and is awaiting the completion of the walls and ceiling to start installing grills and diffusers.
December 2025
The General Trades Contractor completed the metal stud framing and began installing the insulation and hanging the gypsum wall board. The Electrical Contractor completed the in-wall electrical rough, and The Mechanical Contractor started roughing in the new ductwork and piping. Outside in the corridor, the General Trades Contractor removed a section of lockers and completed the wall infill.
November 2025
The General Trades Contractor has completed most of the metal stud framing at both the interior and exterior portions of the building. The in wall electrical rough is ongoing and will continue into mid-December. The Mechanical Contractor is expected to receive most of their equipment the week before the Holiday recess and will work over the holiday recess to install much of their associated piping. The General Trades Contractor will receive a shipment of gypsum wall board and insulation the first week of December and will commence with the installation towards the end of December.
October 2025
The General Trades Contractor has completed selective demolition within both the District Office and Business Office. The mechanical, electrical, and plumbing trades have been working alongside the General Trades Contractor performing disconnects and removals. The General Trades Contractor has started installing metal stud framing within the new spaces and will continue with studs and board in November. Outside, the General Trades Contractor has completed the removal of the sidewalk section and started installing the new building foundations.
August 2025
The Phase III Sitework contractor completed all work within the courtyard and turned it over to the Turf Contractor for installation of the new turf. All work within the courtyard was completed by the middle of August.
July 2025
The Phase III Site Contractor continued work within the main High School Courtyard; new drainage has been installed, the subgrade was prepped, and a portion of the new concrete sidewalk was poured.